The "Space Lifting 53" vessel has completed the installation of the first box girder on the southern shore of Hangzhou Bay.
On November 16, in the construction waters of the Hangzhou Bay Cross-Sea Bridge of the Tong-Su-Jia-Yong High-Speed Railway, the 151st prefabricated box beam was steadily placed on piers 179–180. This marks the first prefabricated box beam set up by the large lifting vessel "Yuhang Crane 53" on the southern shore of Hangzhou Bay, signifying that beam erection at sea has entered a new phase of simultaneous progress from both north and south.
The box beam erected this time is about 80 meters long and weighs approximately 2800 tons, earning the title of "King of Beams Worldwide." The 32,635-ton vessel "Yuhang Crane 53" undertook the sea-based erection task for this box beam.
Hangzhou Bay is one of the world's three major tidal bays, with a maximum tidal range of nearly 9 meters and a maximum flow speed of 5.3 meters per second. During beam erection, safety requirements such as halting lifting when wind strength exceeds level 6, stopping beam retrieval and positioning when wave height exceeds 0.5 meters, or ceasing navigation operations when visibility is below 1500 meters must be strictly enforced. The effective work window on the water annually is less than 200 days.
Unlike conventional bridge construction, the retrieval, transportation, and erection of box beams for the Hangzhou Bay Cross-Sea Bridge's mid-sea approach bridges of the Tong-Su-Jia-Yong High-Speed Railway are all completed at sea. Beam erection operations demand extremely high precision concerning tides, hydrology, meteorology, vessel control, and on-site coordination.
"Beam erection cannot be completed by just one ship; the processes of beam retrieval, transportation, erection, and safety guarding must be meticulously coordinated," explained a relevant official from the South Coast Project Division of the China Communications Second Engineering Bureau. To make optimal use of the limited maritime operation windows, the project employs a "multi-ship collaboration" method by organizing construction with the "Bridge Seagull" vessel responsible for beam retrieval, "Huarun Large Equipment" vessel for beam transportation, "Yuhang Crane 53" vessel for beam erection, and over ten auxiliary ships including tugboats and safety guard boats to ensure smooth beam transfer, positioning, and erection as planned.
The bridge spans the waters of Jiaxing and Ningbo, with multiple steps involved in the approval processes for water-related works and navigation safety. The Ningbo Maritime Safety Administration, together with the Jiaxing Maritime Safety Administration, intervened early to review each plan for "one beam at a time." They focused on verifying the compatibility of beam retrieval, transportation, and erection nodes with tidal windows and coordinated upstream counterparts like Qiantang Logistics and Linlong Wharf to stagger peak operations.
On the day of the operation, maritime authorities of the two cities jointly carried out on-site patrol and safety inspections. Utilizing the Smart Maritime Supervision System, Zhejiang Marine Intelligent Control Platform, and CCTV over-the-horizon monitoring, they implemented real-time electronic patrols of the construction waters. The vessel "Marine Patrol 07128" was stationed early at the outskirts of the core beam installation area, while the guard ship "Longding 168" intercepted small boats downstream.
"Before each beam is securely placed, the key is to monitor the tide, clear the navigation route, and lock in the time window," said the head of the navigation management office of the Ningbo Maritime Safety Administration. The hydrological conditions on the southern side of Hangzhou Bay are more complex, making operations for large vessels more difficult and increasing safety risks. The successful completion of the initial erection ahead of the arrival of cold wave winds reflects the deep collaboration and coordination among various parties contributing to the bridge project.
Currently, all offshore pile foundation and pier construction of the bridge has been completed, with three navigational bridges capped and two navigational bridges joined. The beam erection for the mid-sea approach bridge is accelerating. As a critical vertical line in the nation's "Eight Vertical and Eight Horizontal" High-Speed Railway Network coastal corridor, the Tong-Su-Jia-Yong High-Speed Railway is planned to be ready for operation by the end of 2027. By then, Ningbo to Shanghai and Suzhou will be reachable in one hour, while Jiaxing, Ningbo, and Suzhou will enter a "30-minute travel circle."
-
The "Space Lifting 53" vessel has completed the installation of the first box girder on the southern shore of Hangzhou Bay.3895
-
The cumulative container throughput of Ningbo Beiyi Group over the years has exceeded 70 million TEUs.3218
-
The joint water-based drill for landslide and rockfall emergencies in the Three Gorges Reservoir area was held in Yunyang.3535
-
Yantai Port's vehicle shipments of new energy cars increased by 49.2% year-on-year in the first 10 months of the year.3789
-
Gathering Deep Blue Wisdom and Exploring New Industry Opportunities: The 11th International Diving, Salvage, and Offshore Engineering Technology Forum Held in Qingdao3157